![]() ![]() ![]() |
|---|
|
|
Navigation structures are necessary to make inland waterways viable, year-round transportation corridors. The U.S. Army Corps of Engineers builds, maintains and improves navigation structures on Pittsburgh’s three rivers – the Allegheny, Ohio and Monongahela! The Lower Monongahela River Project
|
|---|
|
Pool 2 |
Pool 3 |
|
ª Dravosburg Borough |
ª Authority of the Borough of Charleroi |
|
ª Elizabeth Borough |
ª City of Monongahela |
|
ª Elizabeth Borough Municipal Authority |
ª Forward Township |
|
ª Elizabeth Township Sanitary Authority |
ª Mon Valley Sewage Authority |
|
ª Glassport Borough |
ª Municipal Authority of the Borough of New Eagle |
|
ªMunicipal Authority of the City of McKeesport |
ª Municipal Authority of the City of Monongahela |
|
ª North Versailles Township Sanitary Authority |
ª New Eagle Borough |
|
ª Sanitary Authority of the City of Duquesne |
ª Pennsylvania Department of Transportation |
|
ª West Elizabeth Sanitary Authority |
ª Pennsylvania Fish and Boat Commission |
|
ª West Mifflin Borough |
ª Rostraver Township |
The government and the Norfolk Southern Corp. will share in the cost of adjusting the Port Perry railroad bridge.
All privately-owned facilities along the Monongahela and Youghiogheny rivers adversely affected by the project pool changes are required to perform any needed adjustments at their own expense according to the navigation servitude powers of the federal government as specified in their Section 10 permits. The Feasibility Report estimated these costs at approximately $111 million, based on gross estimates provided by the owners. Congressional representatives from these areas have been personally involved in discussions with the Pittsburgh District and affected local businesses concerning possible federal assistance for these private relocations.
The Corps of Engineers and the Port of Pittsburgh Commission have established a forum to continue dialogue with these affected owners on likely impacts, technical assistance available from the Corps and potential sources of non-project financial assistance. The Corps routinely interacts with the public on these private relocations during formal presentations to civic groups, participation in community awareness events and publication of the project's newsletter.
When will Dam 3 be removed?
When one new lock chamber
is operational at the new Charleroi Locks and the dredging of Pool 3 is
complete. Although these activities started in the spring of 2005, the
construction has been separated into several contracts and Dam 3 may have to
remain in service through 2016. There is an opportunity to compress the
current schedule by at most three years and begin removal of Dam 3 in 2013.
When will the dredging of the river between Locks 3 and 4
start?
It already has started. In
May 2000, we awarded a $6.4 million contract to GASA, Inc. to dredge between
river miles 40 and 41. This is the first dredging effort. Much more work
remains to be completed. The remaining dredging may be done in increments
as funds become available beginning in 2008, but will have to be complete no
later than 2016 so Dam 3 can be removed.
What will the health concerns for recreational boating be
during the dredging?
The dredging work will not
create any water quality problems. Recreational boaters will have to be
mindful of the location of dredging equipment and operations in the interest
of safe boating.
What will be the approximate loss of river bank?
The new normal pool will be
3.2’ lower than the existing normal pool of elevation 726.9 or elevation
723.7. Here's what that means in relation to what you would normally see.
For instance, say the upper gage at Locks 3 Elizabeth was at 9.7’. This
means that the elevation of pool was 0.7’ above "normal" or at elevation
727.6 (9’ on the gage is normal pool). Therefore, the new normal pool level
will be 3.9’ below the river level you see right now. On average, this will
result in the river receding about 15’ to 25’ from the current shoreline.
How can I find out about any funds available to retrofit my
docks after the project is completed?
The authorized Lower Mon
Project does not include any funds for the adjustment of privately-owned
facilities. The Port of Pittsburgh Commission has investigated other
potential funding sources to assist private owners.
Are the floating pieces of the new Braddock Dam
structurally sound?
Yes. As you probably saw
when Braddock Dam Segments #1 and #2 were floated up the Ohio and
Monongahela Rivers from Leetsdale to Duquesne, they performed as they were
designed. They floated! Each floating dam segment is designed similar to
the hull of a large ship. The only difference is that ships are
manufactured with an inner super structure of steel members and a heavy
plated steel outer skin, while our dam segments' superstructure and skin are
made of concrete that is reinforced with steel bars. When floating, the
segments flex like a ship's hull. So we place our heaviest reinforced
concrete members at the places where we expect the segment to flex the most
and cause the most force to be exerted on the structure. There's plenty of
steel inside all of the concrete to resist the forces and pressures that
each segment is expected to experience. If an accident had occurred during
transport that would have caused a puncture in the outer wall of a dam
segment, like a ship's hull, the arrangement of internal walls are designed
so that only limited compartments would have flooded, which would have
prevented the segment from sinking.
How did we make the floating pieces sink in the right place?
Prior to set-down, each dam
segment had positioning winches and other important equipment attached to it
at the Outfitting Dock at Duquesne. In addition, at the Braddock Locks and
Dam, mooring lines were connected to fixed anchor piles located in various
positions in the river. These fixed anchor piles are located very close to
the new dam's final set-down location. Also, many of the exact survey
points were established and re-verified at this time, along with checks of
the accuracy and preparedness of the survey equipment. Once all of this
initial preparation work was finished, the contractor ensured that weather
and river forecasts were favorable. When the forecasts were favorable, two
towboats towed the dam segment downstream from the Outfitting Dock at
Duquesne to the Braddock Locks and Dam. When the dam segment reached
Braddock, the two towboats carefully positioned the segment at a
predetermined location in close proximity to the final set-down area. Then
the mooring lines from the fixed anchor piles were attached to the
positioning winches on the dam segment. The towboats then disconnect
themselves from the dam segment, thus the winches and mooring lines had
control of the dam segment's final positioning movements. Once the towboats
were disconnected, the winches were operated according to a winching plan
which had been developed for each dam segment. In addition to the winches,
the land wall of Braddock Locks had a guide attached to it where Dam Segment
#1 meets the lock wall. This guide helped align Dam Segment #1 in the
proper position before final set-down. Dam Segment #1 was also fitted with
this guide at the opposite end where Dam Segment #2 connects to it. While
the dam segment was being positioned, its location was extensively surveyed
and crews directed the positioning of the dam segment to a tolerance of plus
or minus 2 inches. Once the dam segment was positioned properly in the
river, water was very slowly pumped into the compartments in the dam
segment. By pumping water into the compartment, the weight of the dam was
increased to a point where it no longer displaced enough water to float, and
began to sink. The pumping was accomplished according to a specific
ballasting procedure, and this procedure ensured that each dam segment sunk
in a slow, level and safe manner. Once the dam segment was set down,
several hydraulic jacking devices that were installed during construction
were used to make any final adjustments that were needed in the dam
segment's position. Finally, each dam segment is concreted into its final
position.
How did the dam segments float? Aren't the pieces too heavy
to float?
The two dam segments were
assembled from 438 reinforced concrete pre-cast panels. These panels weigh
from four to 70 tons each and would not float individually. But they were
interconnected in gridlock fashion and provided with a continuous concrete
slab underneath, creating a boat-like structure with watertight interior
cells. With these cells and the use of transport bulkheads (temporary steel
walls that close an opening), the segments float because of the Law of
Buoyancy. The Law of Buoyancy, which was formulated by the ancient Greek
mathematician Archimedes, simply states that "The upward force on an
immersed object is equal to the weight of the displaced fluid." So
Segment #1, which weighed about 11,000 tons, would need to displace about
11,000 tons of water to stay afloat. Because water weighs 62.4 pounds per
every cubic foot of volume, 11,000 tons of water would occupy a space about
10’ high if spread over a footfall field. And, coincidently, Dam Segment
#1, at 333’ by 104’, is about the size of a football field. So, when
surrounded by water, Dam Segment #1 would theoretically float in about 10’
of water. In actuality, Segment #1 floated at approximately 11’. Dam
Segment #2, at 265’ by 104’ and about 9,000 tons, would also theoretically
float in about 10’ of water. In actuality, Segment #2 also floated at
approximately 11’.
The next logical question would be: "Well, so much for theory, how much did the dam segments really weigh?" The construction and design team carefully monitored the weight of every piece of the segments as they were being built at the Leetsdale Casting Facility. We calculated precise volumes and weights of materials incorporated into each piece and keep a running tally of the actually weight of each segment as work progressed. Based on the final tally, the segments weighed:
v
Dam Segment #1 weighed
22,369,000 pounds (11,184.5 tons)
v
Dam Segment #2
weighted17,169,980 (8,585.0 tons)
With this actual weight information, we can more precisely predicted how deep into the river each dam segment will float for their 27.5 mile trip from the Leetsdale Casting Facility to the outfitting dock at Duquesne. This depth into the water is commonly known to ship builders and operators in the navigation industry as the term "draft." The predicted drafts we
v Dam Segment #1 would draft at 10.4’. (It actually drafted at a little less than 11’.)
v Dam Segment #2 would draft at 10.0’. (It actually drafted at a little over 11’.)
The navigation channel in the Ohio River and the Monongahela River from the Leetsdale Casting Facility to the outfitting dock at Duquesne, and through the Dashields, Emsworth and Braddock locks is deep enough to accommodate these segment drafts.
Did each floating piece fit through the locks?
Yes. The floating dam
segments fit through all the locks. Each segment passed through three locks
in route to Braddock. Lockages occurred at Dashields Locks and Dam and
Emsworth Locks and Dam on the Ohio River and Locks and Dam 2 on the
Monongahela. Each facility is equipped with two lock chambers, with the
larger of the two being 110’ wide. Each segment was 104’ wide at its base,
but there was an additional 1’6” of concrete that projected from the
downstream end of each segment. So the maximum width of each segment was
actually 105’-6”, but as we can see, each segment was able to enter and
leave the large lock chambers and still have about 2-1/2’ of clearance on
each side. This may seem very close, but this is the type of side clearance
that most towboats and barges normally operate with as they pass through our
locks. The length of our larger lock chambers is also suitable to hold each
dam segment.
How long did it take to transport the floating pieces to
the dam site?
The distance from the
Leetsdale Casting Facility to the Outfitting Pier at Duquesne is about 27
miles. The general contractor was limited to a transport speed of no more
than 4 knots. Based on this speed and considering the time necessary for
the lockages at Dashields, Emsworth and Braddock, we predicted it would take
between 18 to 20 hours to make the complete journey.
Segment #1 left Leetsdale about 7:30 a.m. on July 28, 2001 and arrived at Duquesne at 9:15 p.m. that same day. Segment #2 left Leetsdale at 6:55 a.m. on February 27, 2002 and arrived at Duquesne at 9:30 p.m. that same day.
Were timbers being used in the construction of the dam
segments?
Wood and timbers were used
as temporary formwork that shapes the concrete members and slabs in each dam
segment. This material was removed once the concrete was adequately
hardened. Otherwise, there is no other timber or wood permanently
incorporated into the finished work.
Why did we build the floating dam segments at Leetsdale and
not closer to Braddock?
Pittsburgh District elected
not to provide a mandated government-furnished fabrication site for the
float-in concrete segments since an array of options were possible; the
method and location of the fabrication site, which would provide the "best
value for the government" was impossible to predict at the time of
requesting proposals. The source selection method was by the Best Value
Trade-Off methods, wherein offerors submitted both technical and price
proposals. The Joint Venture leased approximately 30 acres of land in
Leetsdale, Pa., prior to submitting a proposal to the district for the
construction of Braddock Dam.
|
||||||
|---|---|---|---|---|---|---|